Heera Field Redevelopment Project

  • Project awarded by ONGC
  • 4 new unmanned wellhead platforms
  • 8 segments rigid pipelines of 6” to 16” dia x 57 km
  • 3 segments flexible submarine pipelines of 140 mm internal diameter x 10.5 km
  • 3 nos. composite cables (23 km) – power and fibre optic
  • Replacement of SPM system in Mumbai High South
  • Platform water depth : 49 to 62 meters

Major highlights :

  • Total structural steel fabrication work exceeds 14000 MT
  • Major modification on a process platform
  • Project completed in May 2010

 